Renovation of anti-corrosion protection including sandblasting and painting steel structure with use of a set of epoxy-polyurethane paints.
Scope of work:
- Cleaning by blasting (sandblasting the structure) to the degree of purity of at least Sa 2 1/2 according to ISO 8501-1
- Painting structure with the use of epoxy primer to the thickness of 100 microns,
- Painting construction with polyurethane topcoat in RAL 7040 colour at a thickness of 50 microns.
Specifications:
- Area: 1900m2,
- Paint System: epoxy-polyurethane,
- Site: Chelm,
- The planned duration: 30 days.
INVESTOR: Cemex Sp.zo.o.
Implementation of the construction and finishing works including anticorrosion works during the reconstruction of the sluice Łabędy in Gliwice
Land development
- Renovation of an electric power transformation substation ,
- Renovation of the technical building of the engine room GG mid-sluice,
- Renovation of the technical building of the southern GG engine room
- Renovation of the technical building of the northern GG engine room
- Renovation and modernization of the main building (control room),
Investor: State Treasury – Regional Water Management in Gliwice.
Duration: 4 months from the date of signing of the contract,
Investment value: about 437 799.1 pln
Participation of PROSPECT GROUP LLC in the Investment: 100%
Anti-corrosion protection includes comprehensive anti-corrosion protection footbridge for pedestrians over the river Soła in Oświęcim
Scope of work:
- Cleaning for Sa2,5 (sandblasting) of steel construction,
- Painting steel construction in three layer system (2x epoxy primer, 1x polyurethane surface)
- Painting steel construction pipeline in polyurethane paints system,
- Reprofiling constructions supports.
Technical data:
- The area of steel constructions: 1700m2,
- The area of pipelines: 400m2
A comprehensive renovation of anti-corrosion protection with sandblasting of steel construction railway viaduct on the national road No. 88
Scope of work:
- Reinforcement steel construction
- Sandblasting steel construction
- Painting steel construction epoxy primer
- Painting steel construction epoxy paint interlaminar,
- Painting steel construction with polyurethane topcoat.
Realization term:
The work carried out with the exclusion of one of the traffic lane in both directions.
More about the renovation can you read on the website of the City of Zabrze at:
http://www.mzdii.zabrze.pl/pl/aktualnosci/item/358-remont-wiadukt-kosciuszki
Industrial anti-corrosion of steel construction industries with the development of technology to the environment C4
Long-term realization included the comprehensive provision of technology and execution services covering:
- Abrasive blasting to Sa 2,5 steel construction
- Painting steel construction in three layer system on the total thickness of 280μm,
- Dismantling redundant construction elements,
Technical data:
- The maximum height of the object: 30m,
- Total area: 3000m2,
- Paint system: Hempel,