      Corrosion protection of steel construction of the flyover and pipe supports

      Corrosion protection of steel construction of the flyover and pipe supports of KONSTAL and Kosciuszko Foundry with the associated works.

      Scope of work:

      • Removing shrubs at the supports pipelines,
      • Truncation of the redundant steel structure projecting beyond the outline of pipe supports with use of angle grinder or acetylene torch,
      • U-profile 120 – 3 pcs,
      • U-profile 100 – 3 pcs,
      • U-profile 80 – 2 pcs,
      • I-beam 80 – 1 piece,
      • I-beam 60 – pcs 3,
      • L-profile 60 – 5 pcs,
      • L-profile 50 – 13 pcs,
      • L-profile 30 – 5 pcs,
      • Closed profile 60×60 – 4 pcs,
      • Closed profile 40×40 – 1 pcs,
      • Tube ø 50 – 3 pcs,
      • Cutting of 6x1000x3000 mm metal sheet and welding of 4 pcs of dismantled L-profile or U-profiles with a length of 1000 mm,
      • Reinforcement of the support legs by welding two 5x350x300 mm and two 5x300x200 mm plate girders,
      • Mechanical cleaning and degreasing of the area of ​​approximately 705 m2 steel structure,
      • Single painting of the structure with priming paint,
      • Double painting of the construction with epoxy paint in the light gray colour,

      Specifications:

      • Paint system: epoxy-polyurethane,
      • Grade surface preparation: Gr 2 (acc. PN-ISO 8501-1),
      • The method of painting: manual, hydrodynamic,
      • Estimated delivery time: 30 days.
      14 April 2014

      Other accomplishments

      Umowa z Lotos Terminale S.A. – naprawa podpór rurociągu

      Anticorrosive mountaineering painting of the exhaust chimney

      Obstruction painting of the GSM h40 tower

      Corrosion protection of steel structures of silos

      Security R15 fire protection