A comprehensive renovation of corrosion protection crane with the development of technology.
Mountaineering renovation Steel Construction crane for PCC Rokita SA with the development of technology renovation.
Works include:
- Sandblasting the degree of structure Sa 2.5 according to ISO 8501,
- Development Technologies Security corrosion in a corrosive environment C5-I Long for durability (above 15 years),
- Implementation of Security corrosion in the system czterowarstwowym to a thickness of 360 microns total,
Technical data:
- Total Construction completion date: 2300 m2,
- Painting System: epoxy – polyurethane
- The total thickness of the coating 360 microns,
- Duration: 35 DAYS
- Corrosive environment: C5-I
Client: PCC Rokita SA
PLACE implementation: Brzeg Dolny POLAND
7 November 2016