      Sandblasting and painting viaduct on the DK 88

      A comprehensive renovation of anti-corrosion protection with sandblasting of steel construction railway viaduct on the national road No. 88

      Scope of work:

      • Reinforcement steel construction
      • Sandblasting steel construction
      • Painting steel construction epoxy primer
      • Painting steel construction epoxy paint interlaminar,
      • Painting steel construction with polyurethane topcoat.

      Realization term:

      • 20 days

      The work carried out with the exclusion of one of the traffic lane in both directions.

      More about the renovation can you read on the website of the City of Zabrze at:

      http://www.mzdii.zabrze.pl/pl/aktualnosci/item/358-remont-wiadukt-kosciuszki

      12 June 2017

      Other accomplishments

      Umowa z Lotos Terminale S.A. – naprawa podpór rurociągu

      Anticorrosive mountaineering painting of the exhaust chimney

      Obstruction painting of the GSM h40 tower

      Corrosion protection of steel structures of silos

      Security R15 fire protection

      Washing elevation M1 Shopping Center

      See all accomplishment